MahaRERA Property Intelligence · Mumbai Suburban

Lodha Kandivali Project - Tower 2

P51800031351 · Akurli Village · promoter Lodha

Certificate SignedDue 31 Jul 2026

Decision Scorecard

The read: Registered, but watch 2 area(s) — nothing red on the record, though the amber points below deserve a direct answer from the promoter before you book.
Regulatory standingGOODRegistration signed and active, no adverse list entry.
Construction progressNOTE~100.0% of the estimated cost incurred (last filing).
Delivery timelineCAUTIONCompletion deadline extended once.
Legal & litigationGOODNo litigation on the MahaRERA record.
Buyer complaintsCAUTION1 complaint(s) filed, none adjudicated yet.
Builder track recordNOTELimited wider portfolio on the MahaRERA register.
Sales / inventoryNOTE~99% of 149 homes sold; 2 available. ₹345.67 Cr of ₹374.59 Cr collected.

What the filing tells you

Synthesis from the MahaRERA record — registration status, the promoter's declared deadline, complaint and litigation history, compliance-filing discipline and the builder of record, read the way a sales team won't volunteer.

Filing its progress reportsThe project has filed quarterly progress reports across 6 year(s) with no current default and no period was ever flagged for default — a promoter still reporting to MahaRERA is one you can hold to the record.
Buyer complaints on the MahaRERA record1 buyer complaint(s) are filed against this project (most recent 20/01/2026). Read the orders in full — an adjudicated complaint is the strongest evidence of how this promoter treats buyers when things go wrong.
⚠ Completion deadline extendedMahaRERA has granted this project 1 formal completion-date extension(s) from 31 Dec 2025 to 31 Jul 2026. A deadline that keeps moving is the clearest, hardest evidence of delivery slippage — read each stated reason (in the Deadline Extensions section) and weigh it before you rely on the current date.
How much is soldOf 149 homes, ~99% are sold/booked with 2 still available per the promoter's inventory filing.
Declared completion still aheadPromoter-declared completion is 31 Jul 2026 (~0 months out) — a commitment on the RERA record you can hold them to.

What I'd Do As A Buyer

  1. Read every buyer complaint and any MahaRERA order in full — it's the clearest evidence of how this promoter behaves when a buyer pushes back.
  2. Confirm the occupancy/completion certificate, the sanctioned plan and its FSI, the 7/12 land extract and title, and your exact carpet area on the agreement — the record shows where to look, not a substitute for your own checks.

Questions To Ask The Builder

The Sanctioned Layout Plan

The layout the promoter actually filed with MahaRERA — rarely shown to buyers. Read where each tower sits relative to the internal roads, the open spaces and the plot boundaries before you pick a flat.

The sanctioned layout plan filed with MahaRERA
The full sanctioned layout plan as filed with MahaRERA — click to enlarge. A scanned document; read positions as approximate and confirm your exact flat against the dimensioned plan.

From the sanctioned site plan, we map every block against the amenities worth being near and the utilities worth avoiding, using each item's position on the plan:

✗ Pump Room✗ Stp/Underground

Of the 8 blocks on the sanctioned plan, 0 sit next to the key amenities and 3 back onto utilities. Where you buy within the project matters:

MixedWing-A, Wing-E, Wing-H, Wing-D and Wing-B
a mix — near an amenity but also within range of a utility; favour higher floors on the amenity side.
Be cautiousWing-C, Wing-F and Wing-G
nearest the pump room — expect odour, pump/generator noise and EMF at the lower floors; prefer higher floors and the elevation facing away, or another block.

A closer read on a few:

Wing-F sits close to the pump room — expect vehicle movement and service noise. Prefer higher floors and the elevation facing away from it, or another block.
Wing-G sits adjoining the pump room — expect vehicle movement and service noise. Prefer higher floors and the elevation facing away from it, or another block.

Positions are read from the sanctioned plan, not surveyed; distances are relative within the plan, not metres. Treat this as where to look first and what to check on a site visit — not a final verdict.

Sales & Inventory

Of 149 homes filed with MahaRERA, 147 are sold/booked (144 with registered agreements + 3 booked) and 2 remain available (~99% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹374.59 Cr in agreement value so far. Of that, ₹345.67 Cr (~92%) is already collected, ₹28.92 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 147 registered agreements, the effective carpet rate is ₹25,337/sqft (typical range ₹24,061–₹28,135) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Ground/Floor 0001932 sqft (86.59 sqm)₹1.23 Cr
Ground/Floor 0002932 sqft (86.59 sqm)₹1.23 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Construction Progress

MahaRERA's cost filing puts construction at ~100.0% of the estimated project cost incurred as of the last certificate (₹105.90 Cr spent against a ₹105.90 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Delivery & Registration

MahaRERA registrationP51800031351
Registered on23 Oct 2021
Promoter-declared completion31 Jul 2026
Current statusCertificate Signed
Against today0 months to the declared date

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time(s). Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202531 Jul 2026We have already uploaded the Full Occupancy Certificate dated 28th April 2025 on the MahaRERA portal for your kind reference. However, the project is currently reflecting under the

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Complaints & Orders

1 complaint(s) are on the MahaRERA record for this project, with orders passed in 0. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1260037220/01/2026Himanshu Shekhar vs Lodha Developers Limitedpending / no order on file

RERA Escrow Account

RERA requires 70% of buyer collections to sit in a designated account spent only on this project. As last filed, that account shows ₹241.97 Cr deposited, ₹198.11 Cr withdrawn for construction, and a closing balance of ₹43.86 Cr.

Project Funding

How the promoter says the project is funded, filed as estimated and actual. On the actual filing the developer's OWN funds are ₹2.13 Cr (~1% of the total) against ₹8.47 Cr borrowed and ₹168.43 Cr from buyer receipts — a read on how much of the developer's own capital is committed versus riding on your money.

FilingOwn fundsBorrowedBuyer receiptsTotal
Actual₹2.13 Cr₹8.47 Cr₹168.43 Cr₹179.03 Cr

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+38 and 149 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Tower 21G+38149-

Unit mix on the filing: 149 habitable floor.

Filed Document Catalog

The documents the promoter has actually filed with MahaRERA for this project — the paperwork trail a buyer's lawyer should read in full. Their presence on the register is a good sign; ask for a certified copy of each before you sign.

Filed documentWhat it is
Promoter PANthe promoter's PAN card
Form 1 — Architect's certificatethe architect's certified % of work completed
Form 3 — CA certificatethe chartered accountant's certificate on funds withdrawn
Form 2 — Engineer's certificatethe engineer's cost-incurred certificate
Title / search reportthe legal title-search report on the land
Form B — Promoter declarationthe promoter's declaration-cum-affidavit
Sanctioned layout planthe approved site layout
Sanctioned building planthe approved building plan

Plus 17 other supporting file(s) on the MahaRERA record.

Engineering, Cost & Professionals

The professionals of record on the MahaRERA filing — the people whose licences are on the line for the certified filings:

RoleName / firmReg. no.
ArchitectVilas Desai & Associate-
ArchitectPradeep KambleCA/87/10471
EngineerK C Shah Consultants-
EngineerDilip BadeNa
Chartered AccountantChirag Sarvaiya & Co-
Chartered AccountantM S K A & Associates105047

Separately, 2 MahaRERA-registered real-estate agent(s) are attached to this project as its sales channel — a measure of the selling machine behind it, not of build accountability. Whoever shows you a flat, verify their MahaRERA agent registration and deal only on the terms in the filed agreement drafts.

Location, Land & Connectivity

Located at Akurli Village, Akurli Road, Mumbai City, Mumbai City, 400101. Per the filed land record, the plot is bounded to the north by P H Housing, to the south by Akurli Road, to the east by D P Road and to the west by I 3 Zone. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Before You Book

This report reads the MahaRERA public record — the promoter's own declarations. Independently confirm: the occupancy/completion certificate, the sanctioned plan and its FSI, the 7/12 land extract and title, the exact carpet area on your agreement, and any complaint/litigation orders in full. Treat the record as where to look first, not a substitute for your own diligence.

Request the report on Lodha Kandivali Project - Tower 2

We analyse Lodha Kandivali Project - Tower 2 in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.