MahaRERA Property Intelligence · Pune

Joyville Hadapsar Sky-Luxe

P52100048338 · Shewalewadi · promoter Joyville Shapoorji

Certificate SignedDue 31 Dec 2026

Decision Scorecard

The read: Registered, but watch 2 area(s) — nothing red on the record, though the amber points below deserve a direct answer from the promoter before you book.
Regulatory standingGOODRegistration signed and active, no adverse list entry.
Construction progressNOTE~51.2% of the estimated cost incurred (last filing).
Delivery timelineCAUTIONDeclared completion is close (~5 months).
Legal & litigationCAUTIONLitigation declared on the project record.
Buyer complaintsGOODNo buyer complaints on record.
Builder track recordGOOD50 projects, none currently flagged.
Sales / inventoryNOTE~95% of 168 homes sold; 8 available. ₹161.02 Cr of ₹203.97 Cr collected.

What the filing tells you

Synthesis from the MahaRERA record — registration status, the promoter's declared deadline, complaint and litigation history, compliance-filing discipline and the builder of record, read the way a sales team won't volunteer.

Filing its progress reportsThe project has filed quarterly progress reports across 5 year(s) with no current default and no period was ever flagged for default — a promoter still reporting to MahaRERA is one you can hold to the record.
⚠ Court litigation on the project recordThe promoter has declared 5 court case(s) in Additional Collector Pune, Bombay High Court and Court Of Civil Judge Senior Division Pune, the oldest from 2009.. Litigation on a project can cloud the land title or stall construction — get a lawyer to pull the cause list and read exactly what is being contested and whether it touches your flat's title.
How much is soldOf 168 homes, ~95% are sold/booked with 8 still available per the promoter's inventory filing.
Builder's wider record is cleanAcross MahaRERA, Joyville Shapoorji runs 50 projects with none currently carrying a regulator flag — a reassuring portfolio signal, though it doesn't erase any issue flagged on this specific project above.
Declared completion still aheadPromoter-declared completion is 31 Dec 2026 (~5 months out) — a commitment on the RERA record you can hold them to.

What I'd Do As A Buyer

  1. Confirm the occupancy/completion certificate, the sanctioned plan and its FSI, the 7/12 land extract and title, and your exact carpet area on the agreement — the record shows where to look, not a substitute for your own checks.

Questions To Ask The Builder

The Sanctioned Layout Plan

The layout the promoter actually filed with MahaRERA — rarely shown to buyers. Read where each tower sits relative to the internal roads, the open spaces and the plot boundaries before you pick a flat.

The sanctioned layout plan filed with MahaRERA
The full sanctioned layout plan as filed with MahaRERA — click to enlarge. A scanned document; read positions as approximate and confirm your exact flat against the dimensioned plan.

From the sanctioned site plan, we map every block against the amenities worth being near and the utilities worth avoiding, using each item's position on the plan:

✗ Stp

Of the 30 blocks on the sanctioned plan, 0 sit next to the key amenities and 3 back onto utilities. Where you buy within the project matters:

MixedBldg 1, Bldg 10, Bldg 11, Bldg 17, Bldg 18, Bldg 19, Bldg 2, Bldg 20, Bldg 21, Bldg 22, Bldg 3, Bldg 4, Bldg 5, Bldg 6, Bldg 7, Bldg 8, Bldg 9, Tower 8, Tower 6, Bldg 12, Bldg 13, Tower 4, Bldg 14, Bldg 15, Bldg 16, Tower 7 and Tower 5
a mix — near an amenity but also within range of a utility; favour higher floors on the amenity side.
Be cautiousTower 3, Tower 2 and Tower 1
nearest the stp — expect odour, pump/generator noise and EMF at the lower floors; prefer higher floors and the elevation facing away, or another block.

A closer read on a few:

Tower 2 sits close to the stp — expect odour and pump/processing noise at the lower floors. Prefer higher floors and the elevation facing away from it, or another block.
Tower 1 sits adjoining the stp — expect odour and pump/processing noise at the lower floors. Prefer higher floors and the elevation facing away from it, or another block.

Positions are read from the sanctioned plan, not surveyed; distances are relative within the plan, not metres. Treat this as where to look first and what to check on a site visit — not a final verdict.

Sales & Inventory

Of 168 homes filed with MahaRERA, 160 are sold/booked and 8 remain available (~95% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹203.97 Cr in agreement value so far. Of that, ₹161.02 Cr (~79%) is already collected, ₹42.95 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 160 registered agreements, the effective carpet rate is ₹10,809/sqft (typical range ₹10,446–₹11,582) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1T02-1041,163 sqft (108 sqm)₹90.53 Lakh
Floor 1T02-1051,163 sqft (108 sqm)₹90.53 Lakh
Floor 1T03-1061,163 sqft (108 sqm)₹90.53 Lakh
PodiumT02-P051,163 sqft (108 sqm)₹90.53 Lakh
PodiumT02-P061,163 sqft (108 sqm)₹90.53 Lakh
PodiumT02-P071,149 sqft (106.7 sqm)₹89.44 Lakh
PodiumT03-P051,163 sqft (108 sqm)₹90.53 Lakh
PodiumT03-P071,163 sqft (108 sqm)₹90.53 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Construction Progress

MahaRERA's cost filing puts construction at ~51.2% of the estimated project cost incurred as of the last certificate (₹102.99 Cr spent against a ₹201.11 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Delivery & Registration

MahaRERA registrationP52100048338
Registered on26 Dec 2022
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Joyville Shapoorji is the promoter of record on 50 project(s), of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 5 court case(s) on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Court Of Civil Judge Senior Division Pune322009Evidence Stage
Bombay High CourtWP No 1311 20192019Pre Admission
Court Of Civil Judge Senior Division PuneSpecial Civil suit no. 32 of 20092009Ongoing
Bombay High CourtWP No. 1311 of 20192019Ongoing
Additional Collector PuneRTS Appeal No. 704/20212021Ongoing

RERA Escrow Account

RERA requires 70% of buyer collections to sit in a designated account spent only on this project. As last filed, that account shows ₹381.20 Cr deposited, ₹380.84 Cr withdrawn for construction, and a closing balance of ₹35.72 Lakh. Withdrawals have drawn the account down to a thin balance — normal late in a build, but worth checking against the construction stage above.

Project Funding

How the promoter says the project is funded, filed as estimated and actual. On the actual filing the developer's OWN funds are ₹0 (~0% of the total) against ₹0 borrowed and ₹179.49 Cr from buyer receipts — a read on how much of the developer's own capital is committed versus riding on your money.

FilingOwn fundsBorrowedBuyer receiptsTotal
Estimated₹0₹0₹179.49 Cr₹179.49 Cr
Actual₹0₹0₹179.49 Cr₹179.49 Cr

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23 and 168 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Tower 21G+2384-
Tower 31G+2384-

Unit mix on the filing: 168 habitable floor.

Filed Document Catalog

The documents the promoter has actually filed with MahaRERA for this project — the paperwork trail a buyer's lawyer should read in full. Their presence on the register is a good sign; ask for a certified copy of each before you sign.

Filed documentWhat it is
Promoter PANthe promoter's PAN card
Commencement certificatethe municipal commencement certificate
Occupancy / completion certificatethe OC/CC — proof of completion
Form 1 — Architect's certificatethe architect's certified % of work completed
Form 3 — CA certificatethe chartered accountant's certificate on funds withdrawn
Form 2 — Engineer's certificatethe engineer's cost-incurred certificate
Title / search reportthe legal title-search report on the land
Form B — Promoter declarationthe promoter's declaration-cum-affidavit
Sanctioned layout planthe approved site layout
Sanctioned building planthe approved building plan

Plus 7 other supporting file(s) on the MahaRERA record.

Engineering, Cost & Professionals

The professionals of record on the MahaRERA filing — the people whose licences are on the line for the certified filings:

RoleName / firmReg. no.
ArchitectAMITVAA SPACCESCA/2015/70787
ArchitectMSK Architect & AssociatesCA/2015/70787
EngineerMr Akshay Lalit Kasar-
EngineerAkshay Lalit kasarEN10-04768
Chartered AccountantM S K C and Associates LLP122071
Chartered AccountantHarshad Doshi & Co.196528
Chartered AccountantPooja Boob432287
Chartered AccountantB R Nagda & co127270
Chartered AccountantBhavesh Nagda-

Separately, 19 MahaRERA-registered real-estate agent(s) are attached to this project as its sales channel — a measure of the selling machine behind it, not of build accountability. Whoever shows you a flat, verify their MahaRERA agent registration and deal only on the terms in the filed agreement drafts.

Location, Land & Connectivity

Located at Shewalewadi, Off Pune Solapur Highway, Mumbai City, Mumbai City, 412307. Per the filed land record, the plot is bounded to the north by 6-7-9-10-6 Part, to the south by Proposed Canal Road 6-7-9-10-2, to the east by 6-7-9-10-6 Part and to the west by 6-7-9-10-6 Part. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Magarpatta / Hadapsar IT6 km
Kharadi / EON IT Park8 km
Pune Junction / city centre11 km
Pune Int'l Airport (Lohegaon)12 km
Baner–Balewadi belt22 km
Hinjewadi Rajiv Gandhi IT Park27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Before You Book

This report reads the MahaRERA public record — the promoter's own declarations. Independently confirm: the occupancy/completion certificate, the sanctioned plan and its FSI, the 7/12 land extract and title, the exact carpet area on your agreement, and any complaint/litigation orders in full. Treat the record as where to look first, not a substitute for your own diligence.

Request the report on Joyville Hadapsar Sky-Luxe

We analyse Joyville Hadapsar Sky-Luxe in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.