Godrej Skyline

PM1260002400007 · Mundhwa · promoter Godrej Properties

Certificate SignedDue 31 Jul 2029

Decision Scorecard

The read: Registered, but watch 2 area(s) — nothing red on the record, though the amber points below deserve a direct answer from the promoter before you book.
Regulatory standingCAUTIONCurrently in QPR default — progress reports have stopped.
Construction progressNOTE~8.7% of the estimated cost incurred (last filing).
Delivery timelineGOODDeclared completion ~36 months out.
Legal & litigationGOODNo litigation on the MahaRERA record.
Buyer complaintsCAUTION1 complaint(s) filed, none adjudicated yet.
Builder track recordGOOD59 projects, none currently flagged.
Sales / inventoryNOTE~32% of 174 homes sold; 119 available. ₹62.42 Cr of ₹192.88 Cr collected.

What the filing tells you

Synthesis from the MahaRERA record — registration status, the promoter's declared deadline, complaint and litigation history, compliance-filing discipline and the builder of record, read the way a sales team won't volunteer.

⚠ Stopped filing progress reportsThe promoter is currently in QPR default (FY 2025-2026) — it has stopped filing the mandatory quarterly progress report MahaRERA requires. A builder that goes quiet on the regulator mid-build is the classic early sign of a stalling project.
Buyer complaints on the MahaRERA record1 buyer complaint(s) are filed against this project (most recent 18/03/2026). Read the orders in full — an adjudicated complaint is the strongest evidence of how this promoter treats buyers when things go wrong.
How much is soldOf 174 homes, ~32% are sold/booked with 119 still available per the promoter's inventory filing.
Builder's wider record is cleanAcross MahaRERA, Godrej Properties runs 59 projects with none currently carrying a regulator flag — a reassuring portfolio signal, though it doesn't erase any issue flagged on this specific project above.
Declared completion still aheadPromoter-declared completion is 31 Jul 2029 (~36 months out) — a commitment on the RERA record you can hold them to.

What I'd Do As A Buyer

  1. The promoter has stopped filing quarterly progress reports — ask for the last filed QPR and the reason for the gap; a builder gone quiet on the regulator is the classic early stall signal.
  2. Read every buyer complaint and any MahaRERA order in full — it's the clearest evidence of how this promoter behaves when a buyer pushes back.
  3. Confirm the occupancy/completion certificate, the sanctioned plan and its FSI, the 7/12 land extract and title, and your exact carpet area on the agreement — the record shows where to look, not a substitute for your own checks.

Questions To Ask The Builder

The Sanctioned Layout Plan

The layout the promoter actually filed with MahaRERA — rarely shown to buyers. Read where each tower sits relative to the internal roads, the open spaces and the plot boundaries before you pick a flat.

The sanctioned layout plan filed with MahaRERA
The full sanctioned layout plan as filed with MahaRERA — click to enlarge. A scanned document; read positions as approximate and confirm your exact flat against the dimensioned plan.

From the sanctioned site plan, we map every block against the amenities worth being near and the utilities worth avoiding, using each item's position on the plan:

✓ Clubhouse✗ Dg Yard✗ Pump Room / Sump✗ Stp✗ Transformer

Of the 16 blocks on the sanctioned plan, 2 sit next to the key amenities and 7 back onto utilities. Where you buy within the project matters:

FavourTower 12 and Tower 4
the pick of the layout — closest to the clubhouse. Target higher floors here.
MixedTower 13, Tower 5, Tower 3, Tower 11, Tower 14, Tower 2 and Tower 6
a mix — near an amenity but also within range of a utility; favour higher floors on the amenity side.
Be cautiousTower 10, Tower 1, Tower 15, Tower 7, Tower 9, Tower 16 and Tower 8
nearest the pump room / sump, stp and transformer — expect odour, pump/generator noise and EMF at the lower floors; prefer higher floors and the elevation facing away, or another block.

A closer read on a few:

Tower 12 is the pick of this layout — it overlooks the clubhouse and is clear of the project's utilities. A unit here, on a higher floor, is where the premium sits.
Tower 4 is the pick of this layout — it overlooks the clubhouse and is clear of the project's utilities. A unit here, on a higher floor, is where the premium sits.
Tower 16 sits adjoining the transformer — expect transformer hum, generator noise on power cuts, and EMF concerns some buyers weigh. Prefer higher floors and the elevation facing away from it, or another block.
Tower 8 sits adjoining the transformer — expect transformer hum, generator noise on power cuts, and EMF concerns some buyers weigh. Prefer higher floors and the elevation facing away from it, or another block.

Positions are read from the sanctioned plan, not surveyed; distances are relative within the plan, not metres. Treat this as where to look first and what to check on a site visit — not a final verdict.

Sales & Inventory

Of 174 homes filed with MahaRERA, 55 are sold/booked (49 with registered agreements + 6 booked) and 119 remain available (~32% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹192.88 Cr in agreement value so far. Of that, ₹62.42 Cr (~32%) is already collected, ₹130.45 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 55 registered agreements, the effective carpet rate is ₹20,920/sqft (typical range ₹20,058–₹49,230) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Construction Progress

MahaRERA's cost filing puts construction at ~8.7% of the estimated project cost incurred as of the last certificate (₹38.55 Cr spent against a ₹445.56 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Delivery & Registration

MahaRERA registrationPM1260002400007
Registered on20 Sep 2024
Promoter-declared completion31 Jul 2029
Current statusCertificate Signed
Against today36 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Godrej Properties is the promoter of record on 59 project(s), of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Complaints & Orders

1 complaint(s) are on the MahaRERA record for this project, with orders passed in 0. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1260149018/03/2026Raosaheb Baban More vs Godrej Properties Limitedpending / no order on file

RERA Escrow Account

RERA requires 70% of buyer collections to sit in a designated account spent only on this project. As last filed, that account shows ₹87.20 Cr deposited, ₹87.00 Cr withdrawn for construction, and a closing balance of ₹20.33 Lakh. Withdrawals have drawn the account down to a thin balance — normal late in a build, but worth checking against the construction stage above.

Project Funding

How the promoter says the project is funded, filed as estimated and actual. On the actual filing the developer's OWN funds are ₹251.34 Cr (~58% of the total) against ₹0 borrowed and ₹87.00 Cr from buyer receipts — a read on how much of the developer's own capital is committed versus riding on your money.

FilingOwn fundsBorrowedBuyer receiptsTotal
Estimated₹286.57 Cr₹0₹147.84 Cr₹434.41 Cr
Actual₹251.34 Cr₹0₹87.00 Cr₹434.41 Cr

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+27 and 174 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Tower 11G+2771-
Tower 21G+2722-
Tower 31G+2722-
Tower 41G+2759-

Unit mix on the filing: 174 habitable floor.

Filed Document Catalog

The documents the promoter has actually filed with MahaRERA for this project — the paperwork trail a buyer's lawyer should read in full. Their presence on the register is a good sign; ask for a certified copy of each before you sign.

Filed documentWhat it is
Title / search reportthe legal title-search report on the land
Form B — Promoter declarationthe promoter's declaration-cum-affidavit
Commencement certificatethe municipal commencement certificate
Sanctioned layout planthe approved site layout
Sanctioned building planthe approved building plan
Form 1 — Architect's certificatethe architect's certified % of work completed
Form 2 — Engineer's certificatethe engineer's cost-incurred certificate
Occupancy / completion certificatethe OC/CC — proof of completion
Form 3 — CA certificatethe chartered accountant's certificate on funds withdrawn
Promoter PANthe promoter's PAN card
Encumbrance certificatethe encumbrance record on the land

Plus 14 other supporting file(s) on the MahaRERA record.

Engineering, Cost & Professionals

The professionals of record on the MahaRERA filing — the people whose licences are on the line for the certified filings:

RoleName / firmReg. no.
ArchitectRSP Design Consultants Pvt. Ltd.CA/89/12572
EngineerDr. Kelkar Designs Pvt. Ltd.CE/BP/33731/23
EngineerSAMARTHA CONSTRO CONSULTANTS LLPPCMC/LE/1090/2023
Chartered AccountantM D Deshpande & Co.166637
Chartered AccountantOmkar Madhav Deshpande036356
Chartered AccountantB S R and Co LLP129402
Chartered AccountantMD Deshpande & Co.166637

Separately, 9 MahaRERA-registered real-estate agent(s) are attached to this project as its sales channel — a measure of the selling machine behind it, not of build accountability. Whoever shows you a flat, verify their MahaRERA agent registration and deal only on the terms in the filed agreement drafts.

Location, Land & Connectivity

Located at Mundhwa, Ghorpadi - Mundhwa Road, Kurla, Mumbai Suburban, 411036. Per the filed land record, the plot is bounded to the north by By Adj CTS No 1258 1267 1269 1270, to the south by By 30 M Wide Proposed DP Road, to the east by By Adj CTS No 1245 and to the west by By 18 M Wide Proposed DP Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Magarpatta / Hadapsar IT2 km
Kharadi / EON IT Park3 km
Pune Junction / city centre4 km
Pune Int'l Airport (Lohegaon)6 km
Baner–Balewadi belt15 km
Hinjewadi Rajiv Gandhi IT Park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Before You Book

This report reads the MahaRERA public record — the promoter's own declarations. Independently confirm: the occupancy/completion certificate, the sanctioned plan and its FSI, the 7/12 land extract and title, the exact carpet area on your agreement, and any complaint/litigation orders in full. Treat the record as where to look first, not a substitute for your own diligence.