Project RERA record · Pune

Ganga Trinity Phase I A1a2a3

by Ganraj Infrastructure LLP · MahaRERA P52100019948 · Certificate Signed · declared completion Dec 2025

Deregistered by MahaRERANot filing quarterly progress reports

Deregistered by MahaRERA. Pune · PISOLI

Deregistered by MahaRERA

This project has been deregistered by MahaRERA. Verify the current status of the registration and whether any alternative arrangements exist for existing buyers.

Not filing quarterly progress reports

The developer is not filing the legally required quarterly progress reports with MahaRERA. This is a compliance violation and makes it impossible to independently track construction progress through the regulator.

Ganga Trinity Phase I A1a2a3 has been deregistered by MahaRERA. Existing buyers should verify whether any alternative arrangement — a new registration, court order, or IRP resolution plan — is in place, and confirm the current status directly with MahaRERA. It also carries 1 additional MahaRERA flag.

On the regulator's record

  • 28 quarterly reporting periods on MahaRERA's compliance schedule — 28 flagged for QPR default, currently in default on QPR filings
  • 1 litigation case on MahaRERA's record for this project

Source: MahaRERA public project record.

Builder track record

Ganraj Infrastructure LLP is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Ganraj Infrastructure LLP

Ganraj Infrastructure LLP
Deregistered by MahaRERAPune

Other RERA-registered projects in Kondhwa Khurd

Adorn Alcazar-II
Hasib Ahmed Shaikh
Advika Phase III - F
Advika Constructions Pvt.ltd
Advika Phase IV-C
Advika Constructions Pvt.ltd
Akshay Galaxy Building A AND D
A. P. Bhandari Developers

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Request the report on Ganga Trinity Phase I A1a2a3

We analyse Ganga Trinity Phase I A1a2a3 in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Free · Risk Snapshot + alerts

The regulatory risk spine for Ganga Trinity Phase I A1a2a3, emailed as a clean scorecard — plus an alert if the RERA status changes:

  • 🔴  Deregistered by MahaRERA

Something went wrong — email hello@quietlist.in.

✓ On its way to your inbox — plus alerts if the status changes.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 11 Jul 2026