Project RERA record · Mumbai, Thane & the MMR

Parinee Eminence Phase 1

by Om Omega Shelters Private Limited · MahaRERA P51900015555 · Certificate Signed · declared completion Mar 2026

Registration suspendedNot filing quarterly progress reports

Registration suspended. Mumbai City · WORLI

Registration suspended

This project's RERA registration is currently suspended. Construction or sales may be halted — confirm the suspension status before making any payment.

Not filing quarterly progress reports

The developer is not filing the legally required quarterly progress reports with MahaRERA. This is a compliance violation and makes it impossible to independently track construction progress through the regulator.

Parinee Eminence Phase 1's RERA registration is currently suspended by MahaRERA. Construction or sales activity may be halted under the suspension order. Confirm the suspension status before making any payment. It also carries 1 additional MahaRERA flag.

On the regulator's record

  • 33 quarterly reporting periods on MahaRERA's compliance schedule — 33 flagged for QPR default, currently in default on QPR filings
  • 2 litigation cases on MahaRERA's record for this project
  • 28 complaints filed with MahaRERA against this project

Source: MahaRERA public project record.

Other RERA-registered projects in Worli

47 Race Course
Deregistered by MahaRERA Akshay Sthapatya Pvt. Ltd.
DB Turf View
Deregistered by MahaRERA Turf Estate JV
Dvayam
Kabra Estate AND Investment Consultants
Godrej Trilogy Seafront
Embellish Houses Private Limited, Akshay
Godrej Trilogy Seaturf
Embellish Houses Private Limited, Akshay
Kalpataru One - Wing A
Kalpataru Properties Limited

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Request the report on Parinee Eminence Phase 1

We analyse Parinee Eminence Phase 1 in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Free · Risk Snapshot + alerts

The regulatory risk spine for Parinee Eminence Phase 1, emailed as a clean scorecard — plus an alert if the RERA status changes:

  • 🔴  Registration suspended

Something went wrong — email hello@quietlist.in.

✓ On its way to your inbox — plus alerts if the status changes.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Jul 2026