Project RERA record · Mumbai, Thane & the MMR

BK. Residency

by OM SAI Construction · MahaRERA P51700051563 · Certificate Signed · declared completion Dec 2027

Not filing quarterly progress reports

Not filing quarterly progress reports. Thane · MURBAD

Not filing quarterly progress reports

The developer is not filing the legally required quarterly progress reports with MahaRERA. This is a compliance violation and makes it impossible to independently track construction progress through the regulator.

BK. Residency is on MahaRERA's non-compliance list for not filing quarterly progress reports. RERA requires developers to report construction progress and sales data to the regulator each quarter — the absence of filings means construction status cannot be independently verified through MahaRERA's public register.

Builder track record

OM SAI Construction is the promoter on 15 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by OM SAI Construction

OM SAI Construction
FlaggedPalghar
OM SAI Construction
FlaggedRaigarh

Other RERA-registered projects in Murbad

Crystal Homes
Developer in insolvency (NCLT) Shreedham Construction Private Limited
Madhusudan Retreat Terraces
Madhusudan Leisure Homes
SAI Krishna Heights
OM SAI Developers
Shree Siddhivinayak Park B1 AND B2
Satyashiv Developers
Shree Siddhivinayak Park C1,c2,c3
Not filing quarterly progress reports Satyashiv Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Request the report on BK. Residency

We analyse BK. Residency in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Free · Risk Snapshot + alerts

The regulatory risk spine for BK. Residency, emailed as a clean scorecard — plus an alert if the RERA status changes:

  • 🔴  Not filing quarterly progress reports

Something went wrong — email hello@quietlist.in.

✓ On its way to your inbox — plus alerts if the status changes.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.