Developer RERA record

Adani Realty

Adani Realty has 16 RERA-registered projects: mixed Gurugram delivery record (5/16 projects with OC); 3 projects past RERA deadline. All figures are the developer's own regulator filings.

Flagged
Delivery signal
5
Completed / delivered
3
Past RERA deadline
Considering a specific Adani Realty project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (5)click to expand
ProjectCityStatus
GROUP HOUSING COLONYGurugramOC issued
SAMSARA AVASAGurugramOC issued
SAMSARA, PART-3GurugramOC issued
SAMSARA PART IGurugramOC issued
SAMSARA VILASA & SAMSARA ARYAGurugramOC issued
Past RERA deadline (3)click to expand

These projects passed their RERA-registered completion date without a recorded OC. Many receive RERA extensions — this is the raw disclosure, not a final verdict. Verify current status directly on the RERA portal before deciding.

ProjectCityRERA deadline
OYSTER ARCADEGurugram2025-11
OYSTER GRANDE-TOWER GGurugram2024-09
SAMSARA PART VGurugram2023-09
Registered, no progress filed yet (8)click to expand
ProjectCity
DOWNTOWN AVENUEGurugram
LUSHLANDSGurugram
OYSTER GREENSGurugram
OYSTER GREENSGurugram
SAMSARA IVANAGurugram
SAMSARA IVANA 2.0Gurugram
THE MARQGurugram
VERISGurugram

Request the report on Adani Realty

We analyse Adani Realty in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Figures are Adani Realty's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.