Project RERA record · Bengaluru

Upkar Habitat Phase 3

K-RERA: PRM/KA/RERA/1251/308/PR/201224/007308

Filing overdue. Upkar Developers · Anekal · due Dec 2029

65%
Built
Sold
2025-Q4
Last filed

Request the report on Upkar Habitat Phase 3

We analyse Upkar Habitat Phase 3 in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

As of 2025-Q4, the K-RERA quarterly filing shows construction at 65%. The K-RERA deadline is 2029-12 — roughly 41 months from now. These figures come from the developer's own quarterly disclosures to K-RERA, not an independent inspection.

Construction, quarter by quarter

2025-Q3 60% → 2025-Q4 65%

Construction has advanced steadily from 60% in 2025-Q3 to 65% as of 2025-Q4 — an average of 5.0 percentage points per quarter across 1 filing.

Built by Upkar Developers. View Upkar Developers's full track record →
Upkar Developers has 5 projects registered in Bangalore.

Other projects by this builder in Bangalore

KHB M/S Upkar Developers
No filings

Other RERA-registered projects in BEML Cooperative Society Layout

1 Lakhmulti Storey Housing Chikanahalli Kamnahali

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.