Project RERA record · Bengaluru
Filing overdue. Rajagopal Reddy · Bengaluru South · due Dec 2028
Official K-RERA registration facts
As of 2025-Q4, the K-RERA quarterly filing shows construction at 63%. 26% of units are reported as sold. The K-RERA deadline is 2028-12 — roughly 29 months from now. These figures come from the developer's own quarterly disclosures to K-RERA, not an independent inspection.
2025-Q3 60% → 2025-Q4 63%
Construction has advanced gradually from 60% in 2025-Q3 to 63% as of 2025-Q4 — an average of 3.0 percentage points per quarter across 1 filing.
Built by Rajagopal Reddy.
Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.