A B Anantha

K-RERA: PRM/KA/RERA/1251/308/PR/100925/008082

Filing overdue. Amaravathi Builders · Anekal · due Jan 2027

55%
Built
0%
Sold
2025-Q4
Last filed

Official K-RERA registration facts

32
Registered units
1,615 sqm
Registered land area

Request the report on A B Anantha

We analyse A B Anantha in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

As of 2025-Q4, the K-RERA quarterly filing shows construction at 55%. 0% of units are reported as sold. The K-RERA deadline is 2027-01 — roughly 6 months from now. These figures come from the developer's own quarterly disclosures to K-RERA, not an independent inspection.

Construction, quarter by quarter

2025-Q3 42% → 2025-Q4 55%

Construction has advanced steadily from 42% in 2025-Q3 to 55% as of 2025-Q4 — an average of 13.0 percentage points per quarter across 1 filing.

Built by Amaravathi Builders.

Other RERA-registered projects in Electronic City

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.