Adarsh Euphoria

K-RERA: PRM/KA/RERA/1251/446/PR/040823/006112

Past its RERA deadline. Shivakar Developers · Bengaluru East · due Jun 2025

92%
Built
Sold
2025-Q4
Last filed

Request the report on Adarsh Euphoria

We analyse Adarsh Euphoria in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Adarsh Euphoria declared a completion date of 2025-06 with K-RERA. As of July 2026, it is 13 months overdue — no completion certificate is on the public register. As of 2025-Q4, the K-RERA quarterly filing shows construction at 92%. These figures come from the developer's own quarterly disclosures to K-RERA, not an independent inspection.

Construction, quarter by quarter

2025-Q3 90% → 2025-Q4 92%

Construction has advanced gradually from 90% in 2025-Q3 to 92% as of 2025-Q4 — an average of 2.0 percentage points per quarter across 1 filing.

Litigation on record (developer self-declared)

K-RERA filings list 1 declared court case touching this project or its underlying land. This is informational, not legal advice — verify case status with the listed court before relying on it.

suit for partition · Senior Civil Judge atBangalore Rural · Case No. 1660 · 2017
a dispute among co-owners or heirs over dividing the property — common in land litigation before a project breaks ground, not a complaint about the project itself.

Built by Shivakar Developers.
Shivakar Developers has 2 projects registered in Bangalore, 1 past RERA deadline.

Other projects by this builder in Bangalore

Adarsh Lumina
Filing overdue · 31% built · 78% sold

What to do next (delayed project)

  1. Ask the developer for the latest RERA extension filing and updated possession date.
  2. If construction is above 80%, check whether an OC application has been filed with the BBMP / local authority.
  3. Review your allotment letter's possession clause for compensation terms on delayed handover.
  4. File a complaint on the K-RERA complaint portal if the delay exceeds the registered timeline.

Your rights as a buyer (RERA)

  • Section 18 — Interest on delay: You are entitled to interest at SBI MCLR+1% on every instalment paid, for each month of delay, until possession or refund.
  • Section 19 — Right to refund: If the builder cannot deliver possession, you may claim a full refund of all amounts paid, with interest.
  • Section 31 — File a complaint: Buyers can file directly with K-RERA. The builder is required to respond within the prescribed period.

Other RERA-registered projects in Gattahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.