Project RERA record · Gurugram

Westerlies Phase-2

HRERA: RERA-GRG-795-2021

Completed · OC granted. Experion · Sector 108 · due Sep 2024

Yes
Completion cert
Sold
Last filed

Request the report on Westerlies Phase-2

We analyse Westerlies Phase-2 in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Westerlies Phase-2 has obtained an occupation/completion certificate from Haryana RERA — the regulator's formal confirmation that the project was completed and is cleared for handover. If you are buying resale, ask the seller to share the OC document and cross-reference with the HRERA registration number on this page.

Built by Experion. View Experion's full track record →
Experion has 17 projects registered in Gurgaon, 11 completed, 2 past RERA deadline.

Other projects by this builder in Gurgaon

HUB 108
Past deadline · 100% sold
Windchants Phase -4,nursery School Site
Past deadline
Commercial Colony
Completed · 69% sold
Residential Plotted Colony
Completed

Other RERA-registered projects in Sector 37D

Figures are from the developer's own disclosures on the Haryana RERA register. "Completion cert" is whether an OC has been granted; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Gurgaon project-delivery tool.