Project RERA record · Gurugram

Ireo Skyon

HRERA: RERA-GRG-1789-2024

Past its RERA deadline. Ireo · Sector -60 · due Nov 2018

No
Completion cert
100%
Sold
2026-Q2
Last filed

Request the report on Ireo Skyon

We analyse Ireo Skyon in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

The developer declared a completion deadline of 2018-11 with Haryana RERA. As of July 2026, 92 months have passed since that date — no completion certificate is on the public record. 100% of 13 units of units have been reported as sold in HRERA filings (as of 2026-Q2). If you are a buyer awaiting possession, the most direct step is to ask the developer for a revised HRERA-filed completion timeline.

Units sold, quarter by quarter

2025-Q1 100% → 2025-Q2 100% → 2025-Q3 100% → 2025-Q4 100% → 2026-Q1 100% → 2026-Q2 100%

Built by Ireo. View Ireo's full track record →
Ireo has 5 projects registered in Gurgaon, 2 completed, 3 past RERA deadline.

Other projects by this builder in Gurgaon

Commercial Colony
Past deadline · 62% sold
THE Corridors
Past deadline · 1% sold
THE Corridors
Completed · 59% sold
THE Corridors
Completed · 54% sold

What to do next (delayed project)

  1. Ask the developer for the HRERA extension order and the revised RERA possession date.
  2. Review your allotment letter's possession clause — it governs your compensation rights for delay.
  3. Check the HRERA complaint portal — previous allottees may have filed complaints about the same project.
  4. File a formal complaint with HRERA if the delay exceeds the registered completion date with no filed extension.

Your rights as a buyer (RERA)

  • Section 18 — Interest on delay: You are entitled to interest at SBI MCLR+1% on every instalment paid, for each month of delay, until possession or refund.
  • Section 19 — Right to refund: If the builder cannot deliver possession, you may claim a full refund of all amounts paid, with interest.
  • Section 31 — File a complaint: Buyers can file directly with HRERA. The builder is required to respond within the prescribed period.

Other RERA-registered projects in Sector-63A

Figures are from the developer's own disclosures on the Haryana RERA register. "Completion cert" is whether an OC has been granted; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Gurgaon project-delivery tool.

Own a unit in Ireo Skyon?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 11 Jul 2026