Project RERA record · Gurugram

Golden Park

HRERA: RERA-GRG-1099-2022

Due soon. Goel & Son'S Developers · Sector 4 · due Jun 2027

No
Completion cert
84%
Sold
2026-Q1
Last filed

Request the report on Golden Park

We analyse Golden Park in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Golden Park's declared HRERA completion deadline of 2027-06 is roughly 11 months away. 84% of 325 units of units have been reported as sold in HRERA filings (as of 2026-Q1). If you have a booking, this is the point to confirm with the developer whether the deadline will be met or whether a HRERA extension is expected.

Units sold, quarter by quarter

2023-Q4 78% → 2024-Q1 79% → 2024-Q2 84% → 2024-Q3 84% → 2024-Q4 84% → 2025-Q1 84%

Filing signals

Escrow: 100% of buyer funds withdrawn (₹418L collected · ₹418L withdrawn per latest QPR). High withdrawal against construction progress warrants scrutiny.

Built by Goel & Son'S Developers.

Other RERA-registered projects in Sector 5

Affordable Group Housing OF 9.95475 Acres

Figures are from the developer's own disclosures on the Haryana RERA register. "Completion cert" is whether an OC has been granted; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Gurgaon project-delivery tool.