Project RERA record · Gurugram

Golden Gate Residency

HRERA: RERA-GRG-1444-2023

On track. Yashvi Homes · Sector-3 · due Jul 2028

No
Completion cert
57%
Sold
2025-Q4
Last filed

Request the report on Golden Gate Residency

We analyse Golden Gate Residency in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Golden Gate Residency's declared deadline of 2028-07 roughly 24 months from now has not yet passed. 57% of 254 units of units have been reported as sold in HRERA filings (as of 2025-Q4).

Units sold, quarter by quarter

2024-Q2 57%

Filing signals

Escrow: 99% of buyer funds withdrawn (₹336L collected · ₹332L withdrawn per latest QPR). High withdrawal against construction progress warrants scrutiny.

Built by Yashvi Homes.

Other RERA-registered projects in Sector 3

Figures are from the developer's own disclosures on the Haryana RERA register. "Completion cert" is whether an OC has been granted; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Gurgaon project-delivery tool.

Own a unit in Golden Gate Residency?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 11 Jul 2026