Developer RERA record

Vr Builders

Vr Builders has 13 RERA-registered projects: 5 projects actively under construction, averaging 38% construction; 3 projects past RERA deadline. All figures are the developer's own regulator filings.

Flagged
Delivery signal
5
Under construction
3
Past RERA deadline
41%
Bengaluru inventory booked

Under construction

Active projects — 5 projects

Construction % is the developer's own latest quarterly filing to the regulator.

ProjectCityProgress
VR ROYAL TOWNSHIPBengaluru48%
VR ROYAL TOWNSHIPBengaluru48%
VR SAPPHIREBengaluru46%
VR SAPPHIREBengaluru46%
VR VIRUPAKSHA TOWNSHIPBengaluru3%
Considering a specific Vr Builders project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past RERA deadline (3)click to expand

These projects passed their RERA-registered completion date without a recorded OC. Many receive RERA extensions — this is the raw disclosure, not a final verdict. Verify current status directly on the RERA portal before deciding.

ProjectCityRERA deadline
VR HANUMAN ENCLAVE 3Bengaluru2025-03
V R GreencityBengaluru2024-12
VR GOKULAM - Block 'B'Bengaluru2021-06
Registered, no progress filed yet (5)click to expand
ProjectCity
V R Royal HomesBengaluru
V R DollarcityBengaluru
VM TOWNSHIP-2Bengaluru
VR GOLDEN ENCLAVE - 3 Bengaluru
VR GOLDEN ENCLAVE - 2Bengaluru

Request the report on Vr Builders

We analyse Vr Builders in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Figures are Vr Builders's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.