Developer RERA record

Sumadhura

Sumadhura has 29 RERA-registered projects: 16 projects actively under construction, averaging 54% construction; 11 projects are past their RERA deadline — a significant track record flag. All figures are the developer's own regulator filings.

Flagged
Delivery signal
16
Under construction
1
Completed / delivered
11
Past RERA deadline
36%
Bengaluru inventory booked
3
RERA complaints filed

Under construction

Active projects — 16 projects

Construction % is the developer's own latest quarterly filing to the regulator.

Bengaluru: 1.0/5 ★☆☆☆☆ (2 MouthShut reviews)

ProjectCityProgress
SARANG BY SUMADHURA PHASE-IBengaluru90%
SUMADHURA PANORAMA PHASE-IBengaluru86%
SUMADHURA PANORAMA PHASE-IBengaluru86%
FOLIUM BY SUMADHURA PHASE-IIIBengaluru85%
SUMADHURA EPITOME-IBengaluru57%
SUMADHURA CAPITOL RESIDENCESBengaluru55%
HIVE BY SUMADHURABengaluru53%
SARANG BY SUMADHURA PHASE-IIBengaluru52%
SUMADHURA PRAMODABengaluru50%
SUMADHURA THRIVEBengaluru43%
SUMADHURA EDITION PHASE-IBengaluru30%
SUMADHURA SOLACE PHASE-IIBengaluru29%
FOLIUM BY SUMADHURA PHASE-IVBengaluru28%
SUMADHURA SOLACE PHASE-IBengaluru26%
SUMADHURA SOLEABengaluru22%
SUMADHURA EDITION PHASE-IIBengaluru21%
Considering a specific Sumadhura project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Delivered projects (1)click to expand
ProjectCityStatus
Z-HUB BY SUMADHURABengaluru100% built
Past RERA deadline (11)click to expand

These projects passed their RERA-registered completion date without a recorded OC. Many receive RERA extensions — this is the raw disclosure, not a final verdict. Verify current status directly on the RERA portal before deciding.

ProjectCityRERA deadline
SUMADHURA SOHAM PHASE-IBengaluru2018-12
SUMADHURA EDEN GARDENBengaluru2021-12
SUMADHURA NANDANAMBengaluru2021-12
SUMADHURA SOHAM PHASE IIBengaluru2019-09
SUMADHURA SUSHANTHAM PHASE IBengaluru2022-09
SUMADHURA CAPITOL TOWERSBengaluru2022-06
ASPIRE AURUM A SUMADHURA VENTUREBengaluru2022-12
SUMADHURA SUSHANTHAM PHASE IIBengaluru2023-03
ASPIRE AMBERBengaluru2024-12
FOLIUM BY SUMADHURA PHASE-IBengaluru2025-06
FOLIUM BY SUMADHURA PHASE-IIBengaluru2025-12
Registered, no progress filed yet (1)click to expand
ProjectCity
Sumadhura Elysium Phase-IBengaluru

RERA complaints & orders

Regulatory record

3 total complaints filed — below average for builders of this scale (42th percentile).

3
Karnataka RERA complaints

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Request the report on Sumadhura

We analyse Sumadhura in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Figures are Sumadhura's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.