Developer RERA record

Ncc Urban

Ncc Urban has 8 RERA-registered projects: 3 projects actively under construction, averaging 45% construction; 5 projects past their RERA deadline. All figures are the developer's own regulator filings.

Flagged
Delivery signal
3
Under construction
5
Past RERA deadline
38%
Bengaluru inventory booked

Under construction

Active projects — 3 projects

Construction % is the developer's own latest quarterly filing to the regulator.

ProjectCityProgress
NCC URBAN GREEN PROVINCE PHASE 2Bengaluru50%
NCC Urban Lake SpringsBengaluru47%
NCC URBAN RETREATBengaluru39%
Considering a specific Ncc Urban project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past RERA deadline (5)click to expand

These projects passed their RERA-registered completion date without a recorded OC. Many receive RERA extensions — this is the raw disclosure, not a final verdict. Verify current status directly on the RERA portal before deciding.

ProjectCityRERA deadline
NCC URBAN MISTY WOODSBengaluru2019-11
NCC URBAN MAYFAIRBengaluru2021-08
NCC Urban Park ViewBengaluru2024-12
NCC Urban Green Province OneBengaluru2025-12
NCC URBAN GREEN PROVINCEBengaluru2020-12

Request the report on Ncc Urban

We analyse Ncc Urban in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Figures are Ncc Urban's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.