Developer RERA record

Essem18 Developers

Essem18 Developers has 6 RERA-registered projects: 3 projects actively under construction, averaging 29% construction; 3 projects past RERA deadline. All figures are the developer's own regulator filings.

Flagged
Delivery signal
3
Under construction
3
Past RERA deadline
23%
Bengaluru inventory booked

Under construction

Active projects — 3 projects

Construction % is the developer's own latest quarterly filing to the regulator.

ProjectCityProgress
KUMARAVANABengaluru49%
The Valley By Essem18 Phase 1Bengaluru30%
Akasha by Essem18Bengaluru8%
Considering a specific Essem18 Developers project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past RERA deadline (3)click to expand

These projects passed their RERA-registered completion date without a recorded OC. Many receive RERA extensions — this is the raw disclosure, not a final verdict. Verify current status directly on the RERA portal before deciding.

ProjectCityRERA deadline
ALAYABengaluru2019-12
THE LITTLE VALLEYBengaluru2020-12
THE VALLEY BY ESSEM18Bengaluru2020-12

Request the report on Essem18 Developers

We analyse Essem18 Developers in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Figures are Essem18 Developers's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.