Developer RERA record

Casagrand

Casagrand has 21 RERA-registered projects: 8 projects actively under construction, averaging 41% construction; 11 projects are past their RERA deadline — a significant track record flag. All figures are the developer's own regulator filings.

Flagged
Delivery signal
8
Under construction
11
Past RERA deadline
83%
Bengaluru inventory booked
137
RERA complaints filed

Under construction

Active projects — 8 projects

Construction % is the developer's own latest quarterly filing to the regulator.

Bengaluru: 1.4/5 ★☆☆☆☆ (151 MouthShut reviews)

ProjectCityProgress
CASAGRAND HAZENBengaluru73%
CASAGRAND FLAMINGOBengaluru62%
Casagrand KeatswayBengaluru60%
CASAGRAND AMORBengaluru35%
CASAGRAND CASABLANCABengaluru26%
CASAGRAND REGALBengaluru13%
CASAGRAND PROMENADEBengaluru7%
CASAGRAND ESTANCIABengaluru3%
Considering a specific Casagrand project? Tell us which one and we'll send you its full RERA record — completion certificate, construction history, quarterly updates.
Past RERA deadline (11)click to expand

These projects passed their RERA-registered completion date without a recorded OC. Many receive RERA extensions — this is the raw disclosure, not a final verdict. Verify current status directly on the RERA portal before deciding.

ProjectCityRERA deadline
Casa Grande LuxusBengaluru2018-04
Casa Grande NeonaBengaluru2019-06
Casagrand RoyceBengaluru2019-12
Casa Grande LorenzaBengaluru2020-10
Casagrand FlorellaBengaluru2022-03
Casagrand Florella Phase 2Bengaluru2022-08
Casagrand OrlenaBengaluru2024-08
CASAGRAND GALILEOBengaluru2025-02
CASAGRAND AQUENEBengaluru2025-06
Casagrand Meridian (70.0% built)Bengaluru2025-11
CASAGRAND ZAIDEN (60.0% built)Bengaluru2026-03
Registered, no progress filed yet (2)click to expand
ProjectCity
CASAGRAND VIVACITYBengaluru
CASAGRAND MOONDANCEBengaluru

RERA complaints & orders

Regulatory record

137 total complaints filed — among the highest complaint volumes of any builder we track (#3 of 50).

136
Karnataka RERA complaints
1
MahaRERA complaints

Complaint counts and order records are sourced directly from RERA portals. A complaint is a filing by a buyer or association; an order is a formal ruling. Not all complaints lead to adverse orders. This is regulatory disclosure, not a verdict.

Request the report on Casagrand

We analyse Casagrand in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Figures are Casagrand's own disclosures on RERA registers, grouped to the consumer-facing developer brand. "Completed" means an OC is on the project's RERA record; construction % is the developer's latest quarterly filing. Past-deadline projects may have received extensions — always verify on the relevant RERA portal. See our market reports for context.