Filing overdue. Affinity Projects · Bengaluru East · due Dec 2027
Official K-RERA registration facts
As of 2025-Q4, the K-RERA quarterly filing shows construction at 82%. 40% of units are reported as sold. The K-RERA deadline is 2027-12 — roughly 17 months from now. These figures come from the developer's own quarterly disclosures to K-RERA, not an independent inspection.
2025-Q3 74% → 2025-Q4 82%
Construction has advanced steadily from 74% in 2025-Q3 to 82% as of 2025-Q4 — an average of 8.0 percentage points per quarter across 1 filing.
Built by Affinity Projects. View Affinity Projects's full track record →
Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.
Own a unit in Vaishnavi Harmony?
Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.
Last checked against the RERA register: 6 Jul 2026