Project RERA record · Bengaluru

Srinidhi-THE Urban Suites

K-RERA: PRM/KA/RERA/1251/446/PR/040524/006858

Filing overdue. Srinidhi Designbuild · Bengaluru East · due Mar 2027

60%
Built
50%
Sold
2025-Q4
Last filed

Official K-RERA registration facts

107
Registered units
7,081 sqm
Registered land area

Request the report on Srinidhi-THE Urban Suites

We analyse Srinidhi-THE Urban Suites in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

As of 2025-Q4, the K-RERA quarterly filing shows construction at 60%. 50% of units are reported as sold. The K-RERA deadline is 2027-03 — roughly 8 months from now. These figures come from the developer's own quarterly disclosures to K-RERA, not an independent inspection.

Construction, quarter by quarter

2025-Q3 51% → 2025-Q4 60%

Construction has advanced steadily from 51% in 2025-Q3 to 60% as of 2025-Q4 — an average of 9.0 percentage points per quarter across 1 filing.

Built by Srinidhi Designbuild.

Other RERA-registered projects in Vinayaka Nagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.