Project RERA record · Bengaluru

Inspira Winds Of Life

K-RERA: PRM/KA/RERA/1251/308/PR/170625/007842

Filing overdue. Iinspira Eco · Anekal · due May 2030

17%
Built
1%
Sold
2025-Q4
Last filed

Official K-RERA registration facts

224
Registered units
18,918 sqm
Registered land area

Request the report on Inspira Winds Of Life

We analyse Inspira Winds Of Life in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

As of 2025-Q4, the K-RERA quarterly filing shows construction at 17%. 1% of units are reported as sold. The K-RERA deadline is 2030-05 — roughly 46 months from now. These figures come from the developer's own quarterly disclosures to K-RERA, not an independent inspection.

Construction, quarter by quarter

2025-Q3 15% → 2025-Q4 17%

Construction has advanced gradually from 15% in 2025-Q3 to 17% as of 2025-Q4 — an average of 2.0 percentage points per quarter across 1 filing.

Built by Iinspira Eco.

Other RERA-registered projects in Sarjapura

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Inspira Winds Of Life?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 6 Jul 2026