Project RERA record · Bengaluru
Filing overdue. Total Environment · Bengaluru East · due May 2028
Official K-RERA registration facts
Request the report on In That Quiet Earth Phase 2B
We analyse In That Quiet Earth Phase 2B in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.
Should you buy in In That Quiet Earth Phase 2B?
The register shows the declared timeline and status — not whether it's a good buy, and Total Environment has 3 of 23 of its other K-RERA projects past their declared date. The report pressure-tests that: Total Environment's delivery record, this project's complaint history, and the sanctioned-plan detail a sales team won't volunteer.
This page is the free K-RERA filing summary. The full RERA Property Intelligence Report gives you everything in the free Risk Snapshot, plus the buy/wait decision — buyer-complaint history, regulatory flags, builder track record, the official unit register, land title, NOCs, and (where the sanctioned plans support it) room-by-room unit data and an annotated site plan. See a real one first:
Sample: Sobha Silicon Oasis → · browse all sample reports →
₹4,999 · delivered within 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · 9028056255@idfcfirst
Paying from outside India? Pay $99 via PayPal or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
As of 2025-Q4, the K-RERA quarterly filing shows construction at 46%. 98% of units are reported as sold. Note: an earlier filing showed a higher construction figure — K-RERA requires developers to report progress each quarter; the latest figure is shown here. The K-RERA deadline is 2028-05 — roughly 22 months from now. These figures come from the developer's own quarterly disclosures to K-RERA, not an independent inspection.
2025-Q3 46% → 2025-Q4 46%
Construction has been reported at 46% across the last 2 quarterly filings with minimal movement — the latest figure (2025-Q4) matches roughly where it was in 2025-Q3.
K-RERA filings list 8 declared court cases touching this project or its underlying land. This is informational, not legal advice — verify case status with the listed court before relying on it.
Built by Total Environment. View Total Environment's full track record →
Buyer reviews · MouthShut
Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.
Own a unit in In That Quiet Earth Phase 2B?
Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.
Last checked against the RERA register: 6 Jul 2026