Ashish ANR Row House

K-RERA: PRM/KA/RERA/1251/446/PR/300623/006026

Past its RERA deadline. Aashish Developer · Bengaluru East · due Dec 2025

79%
Built
33%
Sold
2025-Q4
Last filed

Official K-RERA registration facts

21
Registered units
3,475 sqm
Registered land area

Request the report on Ashish ANR Row House

We analyse Ashish ANR Row House in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

Ashish ANR Row House declared a completion date of 2025-12 with K-RERA. As of July 2026, it is 7 months overdue — no completion certificate is on the public register. As of 2025-Q4, the K-RERA quarterly filing shows construction at 79%. 33% of units are reported as sold. These figures come from the developer's own quarterly disclosures to K-RERA, not an independent inspection.

Construction, quarter by quarter

2025-Q3 77% → 2025-Q4 79%

Construction has advanced gradually from 77% in 2025-Q3 to 79% as of 2025-Q4 — an average of 2.0 percentage points per quarter across 1 filing.

Built by Aashish Developer. View Aashish Developer's full track record →
Aashish Developer has 6 projects registered in Bangalore, 2 past RERA deadline.

Other projects by this builder in Bangalore

Ashish Narayana ROW House
Past deadline · 92% built · 95% sold
Ashish Mnrst Apartment
No filings
Ashish A N Reddy Apartment
No filings

What to do next (delayed project)

  1. Ask the developer for the latest RERA extension filing and updated possession date.
  2. If construction is above 80%, check whether an OC application has been filed with the BBMP / local authority.
  3. Review your allotment letter's possession clause for compensation terms on delayed handover.
  4. File a complaint on the K-RERA complaint portal if the delay exceeds the registered timeline.

Your rights as a buyer (RERA)

  • Section 18 — Interest on delay: You are entitled to interest at SBI MCLR+1% on every instalment paid, for each month of delay, until possession or refund.
  • Section 19 — Right to refund: If the builder cannot deliver possession, you may claim a full refund of all amounts paid, with interest.
  • Section 31 — File a complaint: Buyers can file directly with K-RERA. The builder is required to respond within the prescribed period.

Other RERA-registered projects in Whitefield

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.