Project RERA record · Bengaluru

Aratt Avant Twilight - Phase I

K-RERA: PRM/KA/RERA/1251/446/PR/301223/006522

Filing overdue. Arattukulam Infrastructureconstructions · Bengaluru East · due Jan 2028

70%
Built
57%
Sold
2025-Q4
Last filed

Official K-RERA registration facts

93
Registered units
5,261 sqm
Registered land area

Request the report on Aratt Avant Twilight - Phase I

We analyse Aratt Avant Twilight - Phase I in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

As of 2025-Q4, the K-RERA quarterly filing shows construction at 70%. 57% of units are reported as sold. The K-RERA deadline is 2028-01 — roughly 18 months from now. These figures come from the developer's own quarterly disclosures to K-RERA, not an independent inspection.

Construction, quarter by quarter

2025-Q3 38% → 2025-Q4 70%

Construction has advanced steadily from 38% in 2025-Q3 to 70% as of 2025-Q4 — an average of 32.0 percentage points per quarter across 1 filing.

Built by Arattukulam Infrastructureconstructions.

Other RERA-registered projects in Krishnarajapuram

1 Lakh Multi Storey Bengaluru Housing Bidarahalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Aratt Avant Twilight - Phase I?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 6 Jul 2026