Project RERA record · Bengaluru

Aakriti Emerald

K-RERA: PRM/KA/RERA/1250/304/PR/160925/008096

Filing overdue. Aakriti Projects · Hosakote · due Aug 2028

24%
Built
12%
Sold
2025-Q4
Last filed

Official K-RERA registration facts

130
Registered units
6,373 sqm
Registered land area
1.995
Sanctioned FAR/FSI
143 space(s) (1.10/unit)
Parking disclosed

Request the report on Aakriti Emerald

We analyse Aakriti Emerald in full and send you the RERA Property Intelligence Report — we analyse in 1 working day.

Something went wrong — email hello@quietlist.in instead.

As of 2025-Q4, the K-RERA quarterly filing shows construction at 24%. 12% of units are reported as sold. The K-RERA deadline is 2028-08 — roughly 25 months from now. These figures come from the developer's own quarterly disclosures to K-RERA, not an independent inspection.

Construction, quarter by quarter

2025-Q3 16% → 2025-Q4 24%

Construction has advanced steadily from 16% in 2025-Q3 to 24% as of 2025-Q4 — an average of 8.0 percentage points per quarter across 1 filing.

Built by Aakriti Projects.

Other RERA-registered projects in M V Extenstion

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.